Somerdale Site Development

On this page, we will publish whatever information that we have about the development of the Somerdale site, so please return periodically to catch up! We will also include a timeline to the left of the page as a helpful guide! You can download the full Site Plans here, but be aware that it's 25Mb, so make take a while!

November 2015 - Somerdale Pavilion was officially opened to the members and the public, managed by Aquaterra
Somerdale Pavilion  The Balcony  The Sports Bar
June 2015 - The finishing touches are being made ahead of the grand opening

The New Entrance  The Changing Room Corridor  The Changing Rooms  The Changing Rooms

The Changing Rooms  The Changing Rooms  The Flexible Space

From The Main Bar To The Patio  The Sports Bar & Skittle Alleys  The Sports Bar & Skittle Alleys

The Patio  The Sports Bar & Skittle Alleys  The Kitchen Area

The Kitchen Area  The Foyer  The New Main Pitch

The Balcony Overlooking The Fields  The Playing Fields  The Cadbury Room

The Cadbury Room  The Cadbury Room  The New Car Park

The Main Pitch  The Main Pitch  The New Club

 

October 2014 - The roof is now on, and both the internal and external walls are progressing.  Pitch 1 has now been levelled off and is awaiting ground drainage and flood light conduits are to be installed before the turf is laid on top.

The main football pitch with the new Club beyond    

    

    

    

    

  

September 2014 - New Houses are moving slowly down the field as Pitch 2 goes. The thin brown line just below middle in the bottom four photos is the beginning of the main road into the new estate.

U9's train in the foreground of Pitch 3's development  Looking up past Pitch 3 to the houses  The houses are slowly moving down Pitch 2

Top to bottom panorama of Pitch 2 being redeveloped  Top to bottom panorama of Pitch 2 being redeveloped  Top to bottom panorama of Pitch 2 being redeveloped

Top to bottom panorama of Pitch 2 being redeveloped  Top to bottom panorama of Pitch 2 being redeveloped  Top to bottom panorama of Pitch 2 being redeveloped  Top to bottom panorama of Pitch 2 being redeveloped

September 2014 - Internal walls are added to the new clubhouse.  The Club is taking a step nearer to completion with roof, walls and stairs going up within the structure.  Pitch 1 has had rough spoil laid, raised and levelled so that the finer top graded spoil and soil can be laid and raised by an estimated 300mm to take the new pitch turf. On the east side, curb stones are being laid shaping the car park.

West facing elevation.  Roof on.   West facing elevation.  Roof on.

1st floor west elevation.  Internal walls going up.   1st floor west elevation.  Internal walls going up.   Northwest view. Pitch 1 being levelled and formed

Northwest view. Pitch 1 being levelled and formed   Northwest view across Pitch 1.  New car park being formed.

August 2014 - The new Clubhouse begins to take shape as part of the development.

East elevation of the new Fry Club   East elevation of the new Fry Club   East elevation of the new Fry Club

Looking past the east elevation of the new Fry Club entrance with No.1 Pitch beyond   South west corner looking north onto  Football pitch No1.  This will be slightly raised and have floodlights   South elevation of the new Fry Club

The new Club begins to take shape in the shadow of the original factory   South elevation   West elevation which will have a balcony  that  looks over the playing fields

South west corner looking north onto  Football pitch No1.  This will be slightly raised and have floodlights  North elevation of single storey changing rooms

North west elevation   West elevation of single storey changing rooms

June 2014 - Taylor Wimpey publish an update Newsletter
May 2014 - Taylor Wimpey publish an update Newsletter
December 2013 - Demolishing of "D Block" begins
"D Block" gets demolished
Celebrating the site development approval!
            
November 2011 - A workman dies during part of the internal demolition of the Factory
Police are investigating the death of a workman